Mining
Tailing Storage Facility Extension
BPM conducted an Independent Project Review for one of Australia’s leading mining companies for a proposed Tailings Storage Facility Extension. BPM Provided technical verification on and review to ensure the extension met the minimum stability requirements outlined in ANCOLD. Timing was critical in order to meet board approval and the IPR was completed within a week.
BPM Provided technical verification on and review to ensure the extension met the minimum stability requirements outlined in ANCOLD. Timing was critical in order to meet board approval and the IPR was completed within a week.
Key elements of the review included evaluation of:
- The level of project development and implementation planning to support the investment
- The appropriateness of any technical assurance process
- The appropriateness of the proposed Contracting Strategy, contracts/work packages, market engagement, tender process and evaluation and RTA
- The Capital Cost Estimate, including contingency estimates
- The Implementation Schedule
- Documentation of any material risks and appropriateness of risk mitigation plans.
Outcome
IPR outcome led Client to request BPM Projects to provide further support to the project for the implementation of IPR recommendations..
Explore More Case Studies
Tank Service Swap
Tank service conversion with completion of Concept Study and Detail Design.
Read More →Bund Upgrade Program
Full design and project delivery to ensure bund integrity for a major Fuel Terminal.
Read More →Tallow Storage Optimisation
Detailed analysis for increasing Tallow storage to increase capacity.
Read More →
Contact Us
Ready to discuss your next project? Get in touch with our team.
Ready to discuss your next project?
Get in touch with our team.