The bund upgrade followed the previous Flood Study and Modelling which was completed by BPM Projects.

Key aspects of the program of works included:

  • Subcontractor engagement and supervision for Geotechnical survey and 3D Laser Scan
  • 30% and 70% Design Reviews
  • Constructability Review
  • 3D Model Development
  • Participation in client facilitated HAZOP
  • Multi discipline engineering including Process, Civil/Structural, Piping and Layout.
  • Documents issued to IFC status.