Asset Integrity
Major Hazardous Facility – Dockline Replacement
Performance of FEED study for the replacement of thirteen (13) and removal of four (4) docklines located in a major hazard facility to ensure that the pipelines met a design life of 50 years.
BPM’s scope of work included:
- Cost estimate of project to AACEI Class 3 (-20%/+30% accuracy)
- Preliminary schedule and outage durations to allow for early planning
- Facilitate a preliminary Hazard Analysis (PHA) workshop with Client.
- Undertake Process design for proposed new docklines to AS2885 including but not limited to pipe dimensions, pressure and temperature limits, stress criteria and fluid velocity
- Preliminary design of replacement pipelines.
Explore More Case Studies
Energy
Expert Advisory of internal organisation, project implementation and governance
Discover BPM Projects' evaluation of project execution and governance for implementation of future project success.
Read More →
Energy
Tank Service Swap
Tank service conversion with completion of Concept Study and Detail Design.
Read More →
Asset Integrity
Bund Upgrade Program
Full design and project delivery to ensure bund integrity for a major Fuel Terminal.
Read More →