Gas Main Relocation Project

This was a time-critical project as there was a need to meet the objective of completion within 10 weeks. The terminal was also operational during the construction period civil works, modifications and tie-ins to existing operating plant and equipment.​

This schedule-driven project was expedited by BPM’s strong stakeholder engagement with our client and third parties.

BPM Projects undertook Phase 1- Detail Design which included:​

  • 3D modelling using AutoCAD Plant 3D and generate piping MTO
  • Engagement of 3D laser scanning and underground utilities survey​
  • On-site inspection and engagement with client stakeholders to understand full project scope complexities​
  • Obtaining all regulatory permits and approval.​

​BPM Projects also undertook Phase 2, Procurement & Construct, utilising the design development performed during Phase 1 as the basis for performance. ​

This includes:​

  • Engagement of sub-contractor for the piping and civil construction​
  • Supervision of field construction activities
  • Quality control and inspections.​

Outcome​

BPM Projects successfully delivered the relocation of gas meter and piping with minimal disruption to Terminal Operations and downtime to gas supply.