Energy
Tallow Expansion
Our Tier 1 Client was seeking to provide 5,000m3 of tallow storage at their major terminal in Victoria. The expansion allowed for additional storage for export of larger cargo.
BPM Projects completed:
- Evaluation of eleven (11) site location options, which were reduced to three
- Detailed analysis of the three options to present a single feasible site location
- Project definition to AACEI Class 4 (-20%/30%) estimate with a corresponding schedule, including a defined project scope
- Procurement of quotations from three (3) tank construction companies
- Project risk workshop and mitigation plans.
Outcome
BPM delivered a level of project definition beyond the range for a Class 4 estimate according to AACEI standards. Engineering definition was achieved to 22%.
BPM also identified that two of the three options posed significant execution issues for the project and recommended early that a single option be developed for FEED phase.
Explore More Case Studies
Expert Advisory of internal organisation, project implementation and governance
Discover BPM Projects' evaluation of project execution and governance for implementation of future project success.
Read More →Tank Service Swap
Tank service conversion with completion of Concept Study and Detail Design.
Read More →Bund Upgrade Program
Full design and project delivery to ensure bund integrity for a major Fuel Terminal.
Read More →